Welcome
Road Construction
Project Updates

Sidewalk/Curb
Repair Program

Construction Drawings & Specifications
Street Lights
Stormwater Control
Utility Companies
Right of Way Construction Permits
Maps/GIS
Traffic Engineering
Safety Section
Block Party
Search:
Engineering Department
Construction

Updates/Schedules

The Engineering Department will be very active in 2010 with construction projects throughout the City of Kettering.  Please check back to this page for future updates on the projects listed below.  If you have any questions or concerns, please call the Engineering Department at 296-2436.

Click Here to view Major Contruction Locations and Alternate Routes

Click on the Projects below to view the description and bid results.

South Dixie Resurfacing - Cardington to North Corp Line

Wilmington Pike Resurfacing North- Smithville to North Corp Limit

Wilmington Pike Resurfacing South- Stroop Road to South Corp Limit

East Stroop Road Resurfacing - Far Hills to Shroyer

Crescent Blvd. Rebuild - Cardington to North Corp Line

West Stroop Road - Overland to Far Hills

Dorothy Lane and Wilmington Intersection Reconstruction

2010 Asphalt Overlay Project

Sidewalk, Curb & Drive Approach Repair—2010

2010 Concrete Repair Program

Research Park Street Light Replacment

Kettering Multi-purpose Bike Path

Dorothy Lane Bridge Replacement with Road Closures at Purdue, Sudbury and Galewood

Pole Painting - 2010

Montgomery Square and Renee Drive Resurfacing

Woodman & Patterson/Research Intersection Improvement

 

South Dixie Resurfacing - Cardington to North Corp Line

Project Limit:

South Dixie Highway from Cardington Road to North Corp Line

Project Description:

The project will involve the repairs of the concrete medians and curbs followed by milling and replacing the asphalt. The traffic signal at Sacramento will also be rebuilt and some modifications will be made to the existing lighting.

Contractor:

John R. Jurgensen, Springfield, Ohio

Bid Results:

Click HERE to view the bid results

Status Update:

The anticipated start date is summer 2010.

Project Engineer: Irina Titova-Spang, P.E.

Email: Irina.Titova-spang@ketteringoh.org

Update: July 6, 2010

Click Here to go back to the top

Wilmington Pike Resurfacing North - Smithville to N. Corp Limit

Project Limit:

Starting at Smithville and going to the North Corporation Limit

Project Description: 

The project involves a mill and overlay of Wilmington Pike along with repairing any bad concrete joints in the road base and replacing any concrete curb, drive approaches or sidewalk that needs repaired. The project is being funded by ARRA Federal Stimulus Money.

Contractor:

John R. Jurgensen

Bid Results

Click Here for bid results

Status Update:

The Contractor has completed the roadway work and paving.  At this time, the striping has not been completed.  The City is looking into options to complete the striping as soon as possible.

Project Engineer: Chad Ingle, P.E.

Email: chad.ingle@ketteringoh.org

Update:July 6, 2010

Click Here to go back to the top

Wilmington Pike Resurfacing South- Stroop Road to S. Corp Limit

Project Limit:

Starting at Stroop and going to the South Corporation Limit

Project Description: 

The project involves a mill and overlay of Wilmington Pike along with repairing any bad concrete joints in the road base and replacing any concrete curb, drive approaches or sidewalk that needs repaired.

Contractor:

Barrett Paving, Dayton, Ohio

Bid Results

Click Here for bid results

Status Update:

The construction has started with the replacemnt of the curbs, drive approaches and sidewalk along the project in need of replacement.  At this time, the contractor will not be working on the roadway again until mid July and will finish the above mentioned concrete work.  Following the completion of the concrete, roadway work will begin by repairing bad concrete joints in the roadway base.  Once the concrete base is repaired, the road will be repaved.  It is anticipated the paving will not take place until late August.  Traffic will be reduced during the construction, delays are possible.

Project Engineer: Chad Ingle, P.E.

Email: chad.ingle@ketteringoh.org

Update:July 6, 2010

Click Here to go back to the top

East Stroop Road Resurfacing - Far Hills to Shroyer

Project Limit:

East Stroop Road between Far Hills and Shroyer Road

Project Description: 

The project involves a mill and overlay of Stroop Road along with repairing any bad concrete joints in the road base and replacing any concrete curb, drive approaches or sidewalk that needs repaired. 

Contractor:

R.A. Miller Construction, Hamilton, Ohio

Bid Results :

Click Here for Bid Results

Status Update:

The contractor has completed the project.

Project Engineer: Chad Ingle, P.E.

Email: Chad.Ingle@ketteringoh.org

Update:July 6, 2009

Click Here to go back to the top

Crescent Blvd. Rebuild - Cardington to Glenbeck

Project Limit: 

Crescent Blvd. Rebuild from Cardington to Glenbeck

Project Description:

The project includes the removal and replacement of existing concrete curb along both sides of the street, spot repair of the sidewalk and drive approaches on both sides and new asphalt on the street.

Contractor: 

L.J. DeWeese, Tipp City, Ohio

Bid Results:

Click HERE to view bid results

Status Update:

The contractor plans to begin work in August with a completion date of the first of October.  

Project Engineer: Chad Ingle, P.E.

Email: Chad.Ingle@ketteringoh.org

Updated: July 6, 2010

Click Here to go back to the top

West Stroop Road - Overland to Far Hills

Project Limit: 

West Stroop Road from Overland to Far Hills.

Project Description:

The proposed improvements include providing street lighting for the entire length. The proposed lights between Overland Trail and Southmoor Circle will be placed on the south side of Stroop Road.   Between Southmoor Circle and Far Hills Ave the project will also include providing sidewalks with decorative pavement and pedestrian lighting on short 10’ –12’ poles on both sides of the street.  

Contractor:

To be determined after bid opening

Bid Results:

Available after bid opening

Status Update:

The project is anticipated to bid Fall 2010  

Project Engineer: Joe Roller

Email: Joe.Roller@ketteringoh.org

Updated: January 15, 2010

Click Here to go back to the top

Dorothy Lane and Wilmington Pike Intersection Reconstruction

Project Limit: 

Along East Dorothy Lane, the project extends from Haig Ave. to Hobart St., a distance of approximately 1,400 feet. Along Wilmington Pike, the project extends from Beaverton Drive to Jaybee Court, a distance of approximately 1,300 feet.

Project Description:

This project will involve the reconstruction of the intersection of East Dorothy Lane and Wilmington Pike, including traffic capacity improvements; new pavement, curb, and sidewalks, storm sewers, and street lighting; and replacement of existing traffic signals at Dorothy Lane & Wilmington Pike intersection and the Wilmington Pike & Jaybee Court intersection. A loop road will be constructed on the northwest quadrant of the Dorothy Lane & Wilmington Pike intersection.

This project is being funded by a Federal Congestion Mitigation / Air Quality grant, and by American Recovery and Reinvestment Act Federal Economic Stimulus funds, both of which were provided through the Miami Valley Regional Planning Commission. This project is also being funded by a State grant through the Ohio Public Works Commission.

Click here to see proposed improvements

Contractor:

R.B. Jergens Construction, Vandalia, OH

Bid Results:

Click Here for the Bid Results

Status Update:

Work is continuing on the 12" water main replacement along Wilmington Pike. Installation of the main will be completed the week of July 5, and following pressure and purification testing, new water services will be installed during the month of July. By the end of July, the water main work will be complete, and the contractor will begin work on installing new storm sewers along the east side of Wilmington Pike.

Construction work on Haig Avenue will be underway during the month of July. The work will include the demolition of the three houses on the east side of the road near the Haig & Osage intersection, the installation of storm sewers, and earthwork for the construction of new roadway to connect Haig Avenue to the Wilmington/Jaybee/Betz Crossing intersection. This new roadway is scheduled to be complete by late summer. Haig Avenue remains closed to through traffic while construction is ongoing.

Traffic is being maintained along Wilmington Pike and Dorothy Lane, though motorists should expect additional lane closures and restrictions throughout the duration of the project, as well as potential traffic delays. Motorists are advised to seek alternate routes to bypass the construction area. If you must travel through the construction area, please slow down and be aware of construction equipment and workers in and near the construction area.

Project Engineer: Steve Bergstresser,  P.E.

Email: Steven.Bergstresser@ketteringoh.org

Updated:July 6, 2010

Click Here to go back to the top

2010 Asphalt Overlay Project

Project Location:

This year’s Asphalt Overlay Program includes milling the existing asphalt and placing new asphalt on several residential streets.

Project Description:

Each year the City of Kettering evaluates the roadways to create the annual street maintenance program.  After the streets are evaluated, they are then ranked according to the pavement condition and a list is created for the streets that may be paved this year.  Click Here to see the 2010 Street Paving Map.

Contractor:

John R. Jurgensen

Bid Results:

Click Here for Bid Results

Status Update:

The has completed the concrete work on the project and anticipated to start paving process in late July 2010. 

Project Engineer: Chad Ingle,  P.E.

Email: Chad.Ingle@ketteringoh.org

Updated:May 25, 2010

Click Here to go back to the top

2010 Sidewalk, Curb & Drive Approach Repair

Project Limits:    

Various locations throughout the City of Kettering.

Project Description:  

Includes replacement of existing concrete curb, drive approaches and sidewalks that are in poor condition. This is an assessment program. Anticipated construction to begin this summer.

Contractor:

America's Decorative Concrete, Greenville, Ohio

Bid Results:

Click HERE to view bid results.

Status Update:  

Anticipated start date Summer 2010

Project Engineer:  Diane Wuensch, P.E.

Email:  Diane.Wuensch@ketteringoh.org

Updated:July 6, 2010

Click Here to go to the top

2010 Concrete Repair Program

Project Limit: 

Various locactions throughout the City of Kettering.

Project Description: 

Includes the repair of existing concrete items including street panels, and medians on public streets along with curb and flatwork in City Parks and Facilities.

Contractor:

RA Miller Construction, Hamilton, Ohio.

Bid Results:

Click HERE to view bid results.

Status Update: 

Project anticipated start summer 2010

Project Engineer:  Diane Wuensch, P.E.

Email:  Diane.Wuensch@ketteringoh.org

Updated: July 6, 2010

Click Here to go to the top

Research Park Street Light Replacement

Project Limit: 

Research Blvd. and Founders Drive

Project Description: 

This project is a maintenance project and involves replacing 20 existing steel street light poles with aluminum poles.

Contractor:

Capital Electric Line Builders

Status Update: 

Work has begun and should be complete by the end of June 2010.    

Project Engineer:  Diane Wuensch, P.E.

Email:  Diane.Wuensch@ketteringoh.org

Updated: May 25, 2010

Click Here to go to the top

Kettering Multi-Use Bike Path

Project Limit: 

Full length of Hempstead Station and Stroop Road from Hempstead Station to southwest corner of Wilmington Pike & Stroop Rd intersection

Project Description: 

On Hempstead Station south of David Road the work will be installation of information street signs. The work on Hempstead Station north of David Road and on Stroop Rd the work will include installation of an 8’-10’ wide concrete multipurpose path.

Contractor:

Brumbaugh Construction, Arcanum, Ohio

Bid Results:

Click Here for Bid Results.

Status Update: 

The project has been completed.

Project Engineer:  Joe Roller

Email:  Joe.Roller@ketteringoh.org

Updated: April 30, 2010

Click Here to go to the top

Dorothy Lane Bridge Replacement

Project Limit:

Bridge crossing the South Branch of the Little Beavercreek between Galewood and Purdue

Project Description:

The project involves the removal and replacement of the existing bridge with a wider, single span prestressed concrete composite box beam structure with reinforced concrete wall abutements

Contractor:

R.B. Jergens Contractors, Vandalia, Ohio

Bid Results:

Click Here to review the bid results

Status Update:

The first phase of the project has been completed and the traffic has been shifted to the new bridge.  Work has on Phase 2 which will be to remove and replace the north side of the bridge while maintaining three lanes of traffic on the south side of the bridge.  Although traffic will be maintained on Dorothy Lane, several side streets (Galewood Street, Purdue Road and Sudbury Drive) will be closed at the intersection of Dorothy Lane during the project.  Click Here to view the detour map for the side street closures.  Delays are expected throughout construction.

Project Engineer: Chad Ingle,  P.E.

Email: Chad.Ingle@ketteringoh.org

Updated:July 6, 2010


Click Here to go back to the top

Pole Painting - 2010

Project Limit: 

Street light poles on Spaulding Road—Research Blvd to the North Corp. Line.

Project Description:

This project is a maintenance project and involves painting existing street light poles.

Contractor:

Studebaker Electric

Status Update: 

Work is scheduled to occur May - June 2010.

Project Engineer: Diane Wuensch, P.E.

Email: Diane.Wuensch@ketteringoh.org

Updated: April 30, 2010

Click Here to go back to the top

Montgomery Square and Renee Drive Resurfacing

Project Limit: 

Montgomery Square Drive and Renee Drive.

Project Description:

This project involves repair of concrete curb and then resurfacing of the streets. This project is funded with Community Development/Block Grant (CD/BG) funds.

Contractor:

John R. Jurgensen

Bid Results:

Click Here to View the Bid Results.

Status Update:

The project has been completed.

Project Engineer: Diane Wuensch,  P.E.

Email: Diane.Wuensch@ketteringoh.org

Updated: July 6, 2010

Click Here to go back to the top

Woodman & Patterson/Research Intersection Improvement

Project Limit: 

The project limits include the intersection of Woodman Drive and Patterson Rd/Research Blvd—extending on Woodman Drive from Rainbow Drive on the south to 800 feet north of Patterson Road and extending on Patterson Road to Bauer Street and on Research Blvd to 200 feet east of Rainbow Drive.

Project Description:

This project will improve the alignment of Woodman Drive and add left and right turn lanes in all directions. In addition the traffic signal will be rebuilt. This project is mostly funded with Federal and State funds.

Contractor:

To be determined after bid opening.

Bid Results:

To be published after bid opening.

Status Update:

Anticipated bid date is Winter, 2011.

Project Engineer: Diane Wuensch , P.E.

Email: Diane.Wuensch@ketteringoh.org

Updated:July 6, 2010

Click Here to go back to the top